The DPP conversation usually happens at enterprise scale: data fields, dataspace architectures, connectors. Yet the overwhelming majority of businesses exporting into the EU are SMEs, and their question is far more concrete: how do we do this with the team we have and a budget we can justify?
That is exactly what this guide answers.
Ask the right question first
Instead of "when must I start?", ask: "when will my buyer ask me for the data?" In practice that date is one to two years before the regulatory deadline, because European brands request data from suppliers to prepare themselves.
See the timeline guide.
An eight-week minimum programme
| Week | Task |
|---|---|
| 1 | Scope: which products, which market, which buyer? |
| 2 | Data inventory: what exists in ERP or spreadsheets, and what does not? |
| 3 | Supplier map: who holds the missing fields? |
| 4 | Send the supplier data request (a one-page template) |
| 5 | Decide identifier and carrier (GTIN + QR) |
| 6 | Build a pilot passport for one product |
| 7 | Test label printing and scanning |
| 8 | Review, and turn the template into a standing process |
See a 90-day DPP pilot and a 12-month roadmap.
What not to do
- Do not take on the whole catalogue at once. Trying to collect data for 800 SKUs kills the project.
- Do not wait for perfect carbon data. Phase 1 fields — identity, origin, composition — are the core of the obligation for most products; carbon comes later.
- Do not write your own platform. Registry integration, versioning, signing and the persistence duty are a serious maintenance burden for a small team. See build vs buy.
- Do not just collect PDFs. Move certificate content into structured fields; an archive of PDFs is not a passport.
Is starting in a spreadsheet legitimate?
Yes — to start. A spreadsheet is the fastest way to see your data gap and is still the most common tool for collecting from suppliers. Draw the line here: a spreadsheet is a collection tool, not a publication tool. Versioning, access tiers, signing and registry submission need a platform. See starting DPP with spreadsheets.
Budget: realistic numbers
| Item | Typical range (per year, small brand) |
|---|---|
| DPP platform | €600 – €3,600 |
| Supplier data collection labour | 20–60 person-days (internal cost) |
| Additional label/QR printing cost | < €0.02 per unit |
| GS1 membership (GTIN) | Varies by country |
| LCA / carbon calculation (optional) | €1,500 – €8,000 |
See the cost guide and DPP cost breakdown.
Support schemes
Many countries run digitalisation and green transition grants that can cover consultancy and software costs. Conditions change annually, so check the current calls while you plan the project.
Frequently asked questions
Are SMEs exempt from the DPP?
No. ESPR exempts micro and small enterprises from specific provisions such as the unsold-goods destruction ban, but there is no general DPP exemption — and if you are a supplier, the request reaches you by contract anyway.
How big a team do I need?
At pilot stage, 30–50% of one person's time can be enough. What matters is that the person has access to both product data and the supplier relationship — usually someone in quality or product development.
Do I need a consultant?
Not necessarily. Consultants accelerate projects with complex LCA work or deep multi-tier supply chains. A typical apparel or furniture manufacturer needs a good platform and a disciplined supplier process.
My buyer has not asked yet. Can I wait?
You can, but data collection takes three to nine months. Starting only when the request lands means risking the order.